The Problem
Our client had recently taken over another company and needed to integrate the two head offices into a single central London location.
The new office had to accommodate 40+ desks and associated storage, reception, large and small meeting rooms, hot desk space, computer room, kitchen, post room, etc.

2D Plan

The Solution
The space requirement was calculated and the client found a suitable single floor location close to Marble Arch.
The layout was planned to make use of some existing desks and storage from one of the existing offices, supplemented with new additional desks and other furniture.

Arc

The fit-out included new full height double glazed partitions to meeting rooms and reception, acoustic partitions to the computer room and between meeting rooms, power, voice and data cabling to floor boxes located under desk clusters, audio-visual installations in meeting rooms and air conditioning to computer room. The floor was laid with heavy contract quality carpet tiles.

The Result
The fit-out was completed in six weeks.
We organised and carried out the moves from both existing offices over one weekend, including decommissioning and re-commissioning IT equipment, to ensure that there was minimum disruption to our client’s business.